Bala Community Reserve Fund

Share Bala Community Reserve Fund on Facebook Share Bala Community Reserve Fund on X (formerly Twitter) Share Bala Community Reserve Fund on Linkedin Email Bala Community Reserve Fund link
Aerial image of downtown Bala

Overview & Background

The Township of Muskoka Lakes is seeking input from the community on how to best allocate reserve funds set aside specifically for Bala.

Between 2016 and 2020, the Township received funds from a temporary land lease agreement with Swift River Energy Limited (SREL) during the construction of a hydroelectric generating station in Bala. These funds, totalling $192,400, remain unallocated and are now being made available to support initiatives that align with the community’s priorities.

This effort is part of the Township’s ongoing commitment to its Community Improvement Plan (CIP), which supports the revitalization and enhancement of our downtowns through thoughtful investment and meaningful public input.


Project Update (as of October 2026)

Thank you to everyone who participated in the Township's community engagement opportunities for the Bala Community Reserve Fund.

Following the first round of engagement in 2025, Council directed staff on June 10, 2026, to conduct additional community engagement and call for proposals on the use of the reserve funds.

The second community survey, "Bringing Ideas Into Focus," closed on September 30, 2026. This survey invited the community to help identify priorities for enhancements in Bala that are not already funded or planned through the Township's 10-year Capital Plan.

Township staff are now reviewing the feedback received and preparing a report with recommendations for Council's consideration at a future meeting.

Further updates will be shared on this project page as they become available.

What’s Already Planned?

The Township’s 10-year Capital Plan currently includes the following projects in Bala:

ProjectYearBudget

River St Boat Ramp Replacement

2027

$43,700

Bala Cenotaph Washroom Renovation

2027

$43,700

Bala Bay Dock/Bala Cenotaph Pathway Resurfacing

2027

$27,300

Jaspen Park Beach Repairs

2027

$16,400

Weismiller St Boat Ramp Replacement

2028

$51,400

Weismiller St Dock Redecking

2028

$45,600

Jaspen Park Washroom Renovation

2028

$114,100

Bala Community Centre Playground Replacement

2029

$119,300

Muskoka Lakes Sports Park Playground Replacement

2029

$178,900

Gordon St Dock Replacement

2029

$41,700

Bala Bay Dock Boardwalk Replacement

2030

$186,900

Muskoka Lakes Sports Park Washroom Renovation

2031

$97,700

Muskoka Lakes Sports Park Parking Lot Resurfacing

2031

$130,200

River St Dock Replacement

2031

$39,100

Muskoka Lakes Sports Park Skate Park Replacement

2033

$142,200

Windsor Park Washroom Renovation

2034

$59,400

Muskoka Lakes Sports Park Field Replacement

2035

$1,242,400

These projects will continue to move forward separately from the Bala Community Reserve Fund.


What's Next?

Staff are reviewing the results of both rounds of community engagement to help inform recommendations on the future use of the Bala Community Reserve Fund.

A report outlining the engagement findings and recommendations will be presented to Council at a future meeting. Subscribe to this page for project updates!

Overview & Background

The Township of Muskoka Lakes is seeking input from the community on how to best allocate reserve funds set aside specifically for Bala.

Between 2016 and 2020, the Township received funds from a temporary land lease agreement with Swift River Energy Limited (SREL) during the construction of a hydroelectric generating station in Bala. These funds, totalling $192,400, remain unallocated and are now being made available to support initiatives that align with the community’s priorities.

This effort is part of the Township’s ongoing commitment to its Community Improvement Plan (CIP), which supports the revitalization and enhancement of our downtowns through thoughtful investment and meaningful public input.


Project Update (as of October 2026)

Thank you to everyone who participated in the Township's community engagement opportunities for the Bala Community Reserve Fund.

Following the first round of engagement in 2025, Council directed staff on June 10, 2026, to conduct additional community engagement and call for proposals on the use of the reserve funds.

The second community survey, "Bringing Ideas Into Focus," closed on September 30, 2026. This survey invited the community to help identify priorities for enhancements in Bala that are not already funded or planned through the Township's 10-year Capital Plan.

Township staff are now reviewing the feedback received and preparing a report with recommendations for Council's consideration at a future meeting.

Further updates will be shared on this project page as they become available.

What’s Already Planned?

The Township’s 10-year Capital Plan currently includes the following projects in Bala:

ProjectYearBudget

River St Boat Ramp Replacement

2027

$43,700

Bala Cenotaph Washroom Renovation

2027

$43,700

Bala Bay Dock/Bala Cenotaph Pathway Resurfacing

2027

$27,300

Jaspen Park Beach Repairs

2027

$16,400

Weismiller St Boat Ramp Replacement

2028

$51,400

Weismiller St Dock Redecking

2028

$45,600

Jaspen Park Washroom Renovation

2028

$114,100

Bala Community Centre Playground Replacement

2029

$119,300

Muskoka Lakes Sports Park Playground Replacement

2029

$178,900

Gordon St Dock Replacement

2029

$41,700

Bala Bay Dock Boardwalk Replacement

2030

$186,900

Muskoka Lakes Sports Park Washroom Renovation

2031

$97,700

Muskoka Lakes Sports Park Parking Lot Resurfacing

2031

$130,200

River St Dock Replacement

2031

$39,100

Muskoka Lakes Sports Park Skate Park Replacement

2033

$142,200

Windsor Park Washroom Renovation

2034

$59,400

Muskoka Lakes Sports Park Field Replacement

2035

$1,242,400

These projects will continue to move forward separately from the Bala Community Reserve Fund.


What's Next?

Staff are reviewing the results of both rounds of community engagement to help inform recommendations on the future use of the Bala Community Reserve Fund.

A report outlining the engagement findings and recommendations will be presented to Council at a future meeting. Subscribe to this page for project updates!

  • CLOSED: This survey has concluded.

    Project Overview

    The Bala Community Reserve Fund (BCRF) includes $192,400 in unallocated funds received through a temporary land lease agreement with Swift River Energy Limited (SREL) during construction of the hydroelectric generating station in Bala. The fund is intended to support projects that provide a lasting benefit to the Bala community.

    Following an initial community survey in 2025, the Township is now seeking additional community input to help us prioritize and identify areas that could be enhanced and supported within the $192,400 available.

    Separate from the projects already planned through the Township’s 10-year Capital Plan (see the table in the project overview above), we have identified a few potential areas for enhancements based on the initial community feedback, the funding available, and alignment with the Township’s  Economic Development Strategy and Community Improvement Plan.


    Please note that the examples provided in this survey are intended to illustrate of the scale of project that could be achieved within the level of available funding and are not intended to be a comprehensive or final list of community enhancements.

    Share (Closed) Bala Community Enhancement Survey #2: Bringing Ideas Into Focus on Facebook Share (Closed) Bala Community Enhancement Survey #2: Bringing Ideas Into Focus on X (formerly Twitter) Share (Closed) Bala Community Enhancement Survey #2: Bringing Ideas Into Focus on Linkedin Email (Closed) Bala Community Enhancement Survey #2: Bringing Ideas Into Focus link
  • CLOSED: This survey has concluded. Thank you to everyone who participated.

    From 2016-2020, the Township of Muskoka Lakes received revenues for the temporary lease of Township lands during the construction of a hydroelectric generating station in Bala. These unallocated funds are intended to support future community enhancements in Bala. 

    The Township is now seeking public input on how best to use these funds to reflect local needs and priorities.

    Share (Closed) Bala Community Enhancement Survey #1 on Facebook Share (Closed) Bala Community Enhancement Survey #1 on X (formerly Twitter) Share (Closed) Bala Community Enhancement Survey #1 on Linkedin Email (Closed) Bala Community Enhancement Survey #1 link
Page last updated: 23 Oct 2026, 08:47 AM